Buying in Portugal · Guide

How long does planning approval take in Portugal?

By Martina Pires Cristóvão, architect · November 2026

"How long until we can start building?" is usually the second question foreign clients ask, right after the budget. Portugal has a reputation for slow councils. The 2026 reform set clearer deadlines, but the real timeline still depends on more than the law.

The short answer

The law now gives councils fixed periods for each phase, and if a council misses them, approval can be tacit. Those periods apply phase by phase, not to the whole process. In practice, the quality of the first submission and the number of external opinions decide most of the timeline.

The phases of a licence

1. Design

Before anything is submitted, the architect develops the project from a first study to a licensing project. This is where the plot's rules are checked and where most delays can be prevented.

2. Submission and screening

Applications go through the council's electronic platform; since January 2026 all municipalities use the national platform for planning procedures. The council has 20 days for the initial screening and appraisal, and can ask for missing documents.

3. The architecture project

The council generally has 30 days to decide on the architecture, counted from the end of the previous phase or from the last external opinion. For especially complex operations this can be extended once.

4. External opinions

Some projects need opinions from other bodies: heritage, regional planning, roads, agricultural or ecological reserves. Each one adds its own time, which is why two similar houses in different places can have very different timelines.

5. Engineering projects and the final decision

After the architecture, the engineering projects (structure, water, electricity, energy and others) are submitted. For building works, the council then has 20 days for the final licensing decision.

The faster routes

Where the rules for the plot are already precise, a prior communication lets works begin after a complete submission and five days' notice. A prior information request (PIP) answers feasibility questions in 15 or 30 days and binds the council on the next step. See do I need a permit to renovate in Portugal? for when each route applies.

After the works

For a licensed or communicated building, moving in now requires a prior communication with a declaration from the technicians that the work matches the project. You can occupy the building once that complete communication is submitted.

What really slows projects down

  • Incomplete first submissions, which restart the clock.
  • Illegal existing works that must be legalised before anything new.
  • Unclear rules for the plot, which push the project to a full licence.
  • Decisions changed mid-way by the client after submission.

In short

The law sets the maximum; the preparation sets the reality. A complete, well-prepared first submission is usually what shortens the process most.


If you have a specific property in mind, you can write to us at [email protected].

General information checked in November 2026. It is not legal advice; each property must be assessed individually.