Foreign buyers usually hear one of two things. Either everything in Portugal needs a licence, or since the Simplex reform you can do almost anything. Neither is true, and the difference matters for your budget and your timeline.

Since 1 October 2026 a revised version of the Portuguese building code (RJUE) is in force. Every renovation now falls into one of three routes. This article explains them in plain terms.

The short answer

Repairs and many interior changes need no permit. Works that change the outside of the building, its structure, its floor area or its height usually need either a prior communication to the council or a full licence. The planning rules for your plot decide which, not the seller or the agent.

The three routes

1. Works that need no permit

Conservation works (repairs, restoration, cleaning), interior alterations that do not affect the structure or the exterior, and rebuilding exactly what last legally existed are exempt. So are some smaller items, such as solar panels within the roof limits, roof replacements that keep the same exterior finish, and new windows that keep the original shape and appearance.

Exempt does not mean unregulated. The works must still comply with the master plan, municipal rules and safety standards, and, except for purely interior conservation, the council has to be told five days before work starts. The exemptions do not apply to listed buildings or to buildings inside classified sets or sites.

2. Prior communication (comunicação prévia)

This route applies when a detailed plan or an approved subdivision already fixes what can be built, and also in consolidated urban areas when the project follows the plan, stays within the most common façade height in the street and involves no land handed over to the council.

The advantage is speed: once the file is complete, fees are paid and the council has five days' notice, works can begin. The catch is that a prior communication is not an approval. If the project does not comply, the council can stop the works and order the situation to be corrected, even demolished. The responsibility moves from the council to you and your technicians.

3. A full licence

A licence is still needed when the rules for the plot are not precise enough, for certain works on listed buildings, and for demolitions that are not part of a reconstruction. The council now has fixed deadlines for each phase, explained in how long planning approval takes in Portugal.

What turns a renovation into something bigger

As soon as the footprint, the floor area, the height or the volume grows, the works become an extension, which needs a prior communication or a licence. Enclosing a balcony, converting the attic into rooms or adding a floor all fall here. Whether an extra storey is possible at all is a separate question, covered in can I add a floor to my house in Portugal?

Earlier works that were never licensed are another common problem. Before a new project can be approved, what stands today usually has to match what the council approved, or be legalised first.

How to know before you buy

  • Write down what you want to change – layout, extension, pool, use – before looking at the rules.
  • Check the master plan for the plot and any detailed plan for the area.
  • Compare the house with the council file. Differences are cheaper to discover before the deed than after.
  • Consider a prior information request (PIP). A favourable answer binds the council on the follow-up request; a full PIP can even replace the licence.

In short

Most renovations in Portugal are possible, but not always by the route people assume. Knowing which route applies before signing avoids most surprises in cost and time.